Before a project schedule can be created,the schedule maker should have a ( ) ,an effort estimate for each task,and a resource list with availability for each resource.
- Awork breakdown structure
- Bbaseline
- Csoftware requirements specification
- Dplan
参考答案
A
答案解析
翻译:在项目进度计划制定前,制定者应该有一份工作分解结构,一份针对每个任务的工作量估算,以及可用资源列表。A.工作分解结构 B.基线 C.软件需求说明书 D.计划