Stakeholder management refers to managing communications to satisfy needs of, and resolve issues with, project stakeholders. The ( ) is useful responsible for stakeholder management.
- APMO
- BCIO
- CCCB
- DPM
参考答案
D
答案解析
项目干系人管理是指为满足干系人的需要而与之沟通,并解决所发生的问题。通常,项目经理(PM)负责项目干系人管理。A.项目管理办公室 B.首席信息官 C.变更控制委员会 D.项目经理