A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) . A.assign change tasks to project members B.call A.meeting of the configuration control board C.change the scope baseline
- Apostpone the modification until
- Bseparate enhancement project is funde
- Cafter this project is complete
- Daccording to the original baseline
参考答案
D
答案解析
项目经理认为调整项目范围可以给客户提供增值的服务,项目经理应该怎么做。 选项A是安排任务变更到项目成员,选项B是召集变更控制委员会会议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。 由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金。因此应选择D。