Your have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. ( ) document provides this information.
- AResource assignment matrix
- BChange control plan
- CProject charter
- DClient organization chart
参考答案
B
答案解析
在项目执行的过程中你刚刚获得项目的控制权力,并且需要了解谁具有范围修正的权限,变更控制计划文件提供了该信息。 A.资源分配矩阵 B.变更控制计划 C.项目章程 D.客户组织结构图