单选题来自题库:(高级)信息系统项目管理师

The difference value between Budgeted Cost for Work Performed and Actual Cost for Work Performed is ( ). A.Cost Variance B.Schedule Variance

  • AEarne
  • BValue
  • CCost Performe
  • DIndex

参考答案

A

答案解析

BCWP与ACWP之间的差值是 。 A.成本偏差 B.进度偏差 C.挣值 D. 成本绩效