单选题来自题库:(高级)信息系统项目管理师

Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and( ). A.fast tracking

  • Awhat-if scenario analysis
  • Bresource leveling
  • Ccritical chain metho

参考答案

A

答案解析

进度压缩技术包括赶工和快速跟进。(74) A.快速跟进 B.假设情景分析 C.资源平衡 D.关键链法