单选题来自题库:(高级)信息系统项目管理师

Estimate Activity Duration sis the process of estimating the number of work period sto complete indivities with estimated resources.The tools and technques is not including( ).

  • Aexpert judgment
  • Banalogous estimating
  • Crequirements trace ability matrix
  • Dthree-point estimating

参考答案

C