Estimate Activity Duration sis the process of estimating the number of work period sto complete indivities with estimated resources.The tools and technques is not including( ).
- Aexpert judgment
- Banalogous estimating
- Crequirements trace ability matrix
- Dthree-point estimating
参考答案
C