Project manager believes that modifying the project scop may provide added value for the customer.The project manager should( ) A.change the scope baseline

  • Acontact the customer to determine if the change adds value
  • Bcall
  • Cmeeting of the change control board
  • Dchange the project's objectives

参考答案

C

答案解析

项目经理认为修改项目范围可以为客户提供增值服务。项目经理应该通知项目变更控制委员会召开会议。