Project manager believes that modifying the project scope may provide added value for the customer. The project manager should ( ) . A.change the scope baseline
- Acontact the customer to determine if the change adds value
- Bcall
- Cmeeting of the change control board
- Dchange the project’s objectives
参考答案
C