( )is a project management technique for measuring projectPerformance progress.It has the ability to combine measurements of the project management triangle: scope,time and costs.

  • ACritica1 path method(CPM)
  • BEarned value management(CEV)
  • CNet present value method(NPVM)
  • DExpert judgment method(EJM)

参考答案

B