The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ) .

  • Ahe project is ahead of its planned schedule
  • Bless work was completed than was planned t
  • Cthe cost overrun for work completed
  • Dthe cost underrun of performance to date

参考答案

B