The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ) .
- Ahe project is ahead of its planned schedule
- Bless work was completed than was planned t
- Cthe cost overrun for work completed
- Dthe cost underrun of performance to date
参考答案
B