The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .
- AChang control board
- BProject management office
- CProject manager
- DConfiguration management officer
参考答案
C
答案解析
实施整体变更控制过程是从项目开始到项目结束并且是项目经理的最终责任。