A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks mostlikely, and 12 weeks pessimistically. which would appear on the chart ( ) .
- A4 weeks
- B5 weeks
- C6 weeks
- D7 weeks
参考答案
B