The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()

  • AMeasure, delay, record, distribute, analyze, and direct
  • BPlan, schedule, monitor, control, report, and forecast
  • CPromote, highlight, monitor, control, forecast, and report
  • DEmphasize, visualize, analyze, conceptualize, report and record

参考答案

B

答案解析

项目进度计划不只是一个列出项目规定活动的时间表,而且还是一个用于决策的工具。如:进度计划可以被项目管理团队用来(73)。A.检测,延时,记录,分发,分析和直接B.计划,日程安排,监督,控制,报告和预测C.提升,亮点,监视,控制,预测和报告D.重点化,可视化,分析,概念化,报告和记录