[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-254410":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},254410,97,1,"单选题","项目退出通常需要选择适当的退出时机，下列关于项目退出的一般顺序排列正确的是（ ）。 Ⅰ．进行交易结算并进行退出后的评估与评价 Ⅱ．评估公开上市、股权转让等不同退出路径的收益 Ⅲ．设计退出方案 Ⅳ．进行退出启动前的准备",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Ⅰ、Ⅱ、Ⅲ、Ⅳ",false,{"key":16,"text":17,"correct":18},"B","Ⅱ、Ⅲ、Ⅳ、Ⅰ",true,{"key":20,"text":21,"correct":14},"C","Ⅰ、Ⅲ、Ⅳ、Ⅱ",{"key":23,"text":24,"correct":14},"D","Ⅰ、Ⅱ、Ⅳ、Ⅲ","项目退出通常需要选择适当的退出时机，评估公开上市、股权转让等不同退出路径的收益，进而设计退出方案；进行退出启动前的准备；启动退出程序后，监控整个项目退出过程；最终进行交易结算并进行退出后的评估与评价。",{"id":6,"name":27,"category":28,"favorite":29},"私募股权投资基金基础知识","经济金融",0]