[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-223072":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},223072,92,3,"判断题","采用年数总和法对项目固定设备折旧时，在固定资产折旧到期前两年，要将固定资产账面净值扣除预计残值后的净额平均摊销。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"采用双倍余额递减法对项目固定设备折旧时，在固定资产折旧到期前两年，要将固定资产账面净值扣除预计残值后的净额平均摊销。年数总和法无此规定。",{"id":6,"name":21,"category":22,"favorite":23},"(中级)公司信贷","经济金融",0]