[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-219996":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},219996,92,1,"单选题","下列选项中，属于项目建设条件分析中外部条件的是（ ）。[2013年11月真题]",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","拟建项目的物力条件",false,{"key":16,"text":17,"correct":14},"B","拟建项目的人力条件",{"key":19,"text":20,"correct":21},"C","拟建项目的建筑施工条件",true,{"key":23,"text":24,"correct":14},"D","拟建项目的财务资源条件","拟建项目的建设条件包括项目自身的内部条件和客观存在的外部条件。内部条件是指拟建项目的人力、物力、财务资源条件；外部条件是指建筑施工条件、相关项目的协作配套条件以及国家规定的环境保护条件。",{"id":6,"name":27,"category":28,"favorite":29},"(中级)公司信贷","经济金融",0]