[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-219991":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},219991,92,1,"单选题","下列关于项目盈利能力分析表述错误的是（ ）。[2014年6月真题]",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计算项目财务净现值时，设定的折现率越高，财务净现值越高",true,{"key":16,"text":17,"correct":18},"B","净现值率越大，项目的效益就越好",false,{"key":20,"text":21,"correct":18},"C","项目投资回收期小于基准投资回收期时，表明该项目能在规定时间内收回投资",{"key":23,"text":24,"correct":18},"D","财务净现值大于零，表明项目的获利能力超过基准收益率或设定收益率","A项，一个项目的财务净现值是指项目按照基准收益率或根据项目的实际情况设定的折现率，将各年的净现金流量折现到建设起点(建设期初)的现值之和，设定的折现率越高，财务净现值越低。",{"id":6,"name":27,"category":28,"favorite":29},"(中级)公司信贷","经济金融",0]