[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-219989":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},219989,92,1,"单选题","下列关于项目评价的说法，正确的是（ ）。[2015年5月真题]",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","财务内部收益率为23．95％，项目基准收益率为25．35％，则项目可以接受",false,{"key":16,"text":17,"correct":18},"B","投资回收期为3．5年，基准投资回收期为3．9年，则该项目能在规定的时间内收回投资",true,{"key":20,"text":21,"correct":14},"C","A项目的净现值率为2．38，B项目的净现值率为2．67，则应该选择A项目进行投资",{"key":23,"text":24,"correct":14},"D","财务净现值为-3．55，则项目的获利能力超过基准收益率","当项目投资回收期小于或等于基准投资回收期时，表明该项目能在规定的时间内收回投资。A项，财务内部收益率低于基准收益率时，项目不可以接受；C项，净现值率越大，项目效益越好；D项，财务净现值大于零时，表明项目的获利能力超过基准收益率或设定收益率。",{"id":6,"name":27,"category":28,"favorite":29},"(中级)公司信贷","经济金融",0]