[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-219880":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},219880,92,2,"多选题","下列关于项目生产所需的燃料及动力供应条件分析的说法，正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","所需燃料通常有煤炭、石油和天然气",true,{"key":16,"text":17,"correct":14},"B","所需动力主要有电力和蒸汽",{"key":19,"text":20,"correct":14},"C","要依据产品生产过程、成本、质量、区域环境来选择燃料种类",{"key":22,"text":23,"correct":24},"D","要根据当地水源分布、水质情况分析用水量",false,{"key":26,"text":27,"correct":14},"E","耗电量大又要求连续生产的工业项目，要分析估算项目最大用电量、高峰负荷、","ABCE","D项，在项目评估时，要根据项目对水源、水质的要求，计算出项目用水量，再结合当地的供水价格，分析耗水费用对产品成本的影响。",{"id":6,"name":31,"category":32,"favorite":33},"(中级)公司信贷","经济金融",0]