[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-219834":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},219834,92,2,"多选题","财务预测审查的内容有( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","成本",true,{"key":16,"text":17,"correct":14},"B","利润",{"key":19,"text":20,"correct":14},"C","税金",{"key":22,"text":23,"correct":14},"D","销售收入",{"key":25,"text":26,"correct":14},"E","项目递延资产原值的确定及其折旧和摊销办法","ABCDE","财务预测审查是对项目可行性研究报告财务评价的基础数据进行审查，审查的内容主要有：①项目总投资、建设投资、流动资金的估算；②项目固定资产、无形资产、递延资产原值的确定及其折旧和摊销办法；③成本；④销售收入；⑤税金；⑥利润。",{"id":6,"name":30,"category":31,"favorite":32},"(中级)公司信贷","经济金融",0]