[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-219803":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},219803,92,2,"多选题","银行在分析项目工艺技术方案时，应考虑技术来源的经济性，这就要考虑工艺技术的运营成本。工艺技术运营成本包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","人员工资",true,{"key":16,"text":17,"correct":14},"B","原材料及能源消耗费",{"key":19,"text":20,"correct":14},"C","工艺设备及厂房折旧费",{"key":22,"text":23,"correct":24},"D","贷款利息等财务费用",false,{"key":26,"text":27,"correct":14},"E","维护运转费","ABCE","工艺技术营运成本决定了工艺技术方案的经济收益。工艺技术营运成本包括原材料及能源消耗费、维护运转费、人员工资、工艺设备及厂房折旧费。",{"id":6,"name":31,"category":32,"favorite":33},"(中级)公司信贷","经济金融",0]