[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-219762":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},219762,92,2,"多选题","决定一个项目规模大小的因素主要有( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","生产技术状况",true,{"key":16,"text":17,"correct":14},"B","国民经济发展规划",{"key":19,"text":20,"correct":14},"C","资金与基本投入物",{"key":22,"text":23,"correct":14},"D","项目所处行业的技术经济特点",{"key":25,"text":26,"correct":14},"E","土地使用权的取得","ABCDE","制约一个项目规模大小的因素主要有以下几个：①国民经济发展规划、战略布局和有关政策；②项目所处行业的技术经济特点；③生产技术和设备、设施状况；④资金和基本投入物；⑤其他生产建设条件(土地使用权的取得、交通运输、环境保护、人员编制、设备供应等)。",{"id":6,"name":30,"category":31,"favorite":32},"(中级)公司信贷","经济金融",0]