[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-219685":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},219685,92,1,"单选题","贷款项目建设的必要性评估不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目所属行业当前整体状况分析，国内外情况对比，发展趋势预测，项目所生产产品的生命周期分析",false,{"key":16,"text":17,"correct":14},"B","项目产品市场情况分析和项目产品的竞争力分析",{"key":19,"text":20,"correct":14},"C","贷款项目是否符合国家产业政策，是否符合国家总体布局和地区经济结构的需要",{"key":22,"text":23,"correct":24},"D","资源条件能否满足项目需要，原辅材料、燃料供应是否有保障，是否经济合理",true,"D项属于项目建设配套条件评估需要考虑的内容。",{"id":6,"name":27,"category":28,"favorite":29},"(中级)公司信贷","经济金融",0]