[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-219221":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},219221,92,1,"单选题","测算固定资产贷款需求量时，计算资本金基数的总投资是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目的固定资产贷款投资",false,{"key":16,"text":17,"correct":14},"B","项目的铺底流动资金",{"key":19,"text":20,"correct":21},"C","项目的固定资产贷款投资与铺底流动资金之和",true,{"key":23,"text":24,"correct":14},"D","项目的固定资产贷款投资与铺底流动资金的比例","暂无解析",{"id":6,"name":27,"category":28,"favorite":29},"(中级)公司信贷","经济金融",0]