[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-219165":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},219165,92,1,"单选题","?测算固定资产贷款需求量时，基本预备费一般按( )测算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","固定资产投资中工程费用",false,{"key":16,"text":17,"correct":14},"B","固定资产投资中工程费用和其他费用之和",{"key":19,"text":20,"correct":21},"C","固定资产投资中工程费用和其他费用之和的10％",true,{"key":23,"text":24,"correct":14},"D","固定资产投资中工程费用和其他费用之和的10％，并按10％物价指数调整","基本预备费一般按固定资产投资中工程费用和其他费用之和的10％测算。计算涨价预备费的物价指数一般按10％掌握，对设备价格基本确定的项目比例可适当降低。",{"id":6,"name":27,"category":28,"favorite":29},"(中级)公司信贷","经济金融",0]