[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-217257":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},217257,92,1,"单选题","某项目的净现金流量如下，则其投资回收期为（ ）。[2014年11月真题]",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":14},"B","3．67",{"key":19,"text":20,"correct":14},"C","3．5",{"key":22,"text":23,"correct":24},"D","3．33",true,"投资回收期的计算公式为：投资回收期=[累计净现金流量开始出现正值年份数]-1+[上年累计净现金流量绝对值／当年净现金流量]，其中，“当年净现金流量”的“当年”指“累计净现金流量开始出现正值年份”。由题可知第四年累计净现金流量开始为正，所以投资回收期=4-1+20／60≈3．33(年)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级)公司信贷","经济金融",0]