[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277715":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":28},1277715,868,1,"单选题","外墙抹灰施工工艺的流程是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","基层清理→找规矩→做灰饼、冲筋→贴分格条→抹底层灰→抹中层灰→抹面层灰→滴水线（槽）→清理",true,{"key":16,"text":17,"correct":18},"B","找规矩→基层清理→做灰饼、冲筋→贴分格条→抹底层灰→抹中层灰→抹面层灰→清理",false,{"key":20,"text":21,"correct":18},"C","找规矩→基层清理→做灰饼、冲筋→抹底层灰→抹中层灰→滴水线（槽）→抹面层灰→清理",{"key":23,"text":24,"correct":18},"D","基层清理→找规矩→做灰饼、冲筋→抹底层灰→抹中层灰→贴分格条→滴水线",{"key":26,"text":27,"correct":18},"E","）→抹面层灰→清理","",{"id":6,"name":30,"category":31,"favorite":32},"装饰方向-通用基础","建筑工程",0]