[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277699":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1277699,868,1,"单选题","下列施T项目管理程序的排序正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标、签订合同一施工准备一施工一验收交工与结算一用后服务",true,{"key":16,"text":17,"correct":18},"B","施工准备一投标、签订合同一施工一验收交工与结算一用后服务",false,{"key":20,"text":21,"correct":18},"C","投标、签订合同一施工一施工准备一验收交工与结算一用后服务",{"key":23,"text":24,"correct":18},"D","投标、签订合同一施工准备一施工一验收交工一用后服务与结算","",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-通用基础","建筑工程",0]