[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277456":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1277456,867,3,"判断题","施工质量计划涵盖的范围,按整个工程项目质量控制的要求,应与建筑安装工程,施工任务的实施范围相一致,以此保证整个项目建筑安装工程的施工质量总体受控。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"【知识点】 施工质量计划的覆盖范围与施工任务实施范围的一致性要求。 【答案解析】 正确。题干说法符合施工质量控制原则，即质量计划范围应与施工实施范围一致，以确保整体质量受控。",{"id":6,"name":21,"category":22,"favorite":23},"装饰方向-岗位技能","建筑工程",0]