[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277451":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1277451,867,3,"判断题","对于建设工程项目管理者而言,人、技术、管理和环境因素,是不可控因素。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"【知识点】 建设工程项目管理的可控与不可控因素区分 【答案解析】 题干说法错误。人、技术、管理属于可控因素，环境因素部分可控，并非全部不可控，因此应选“错误”（B）。",{"id":6,"name":21,"category":22,"favorite":23},"装饰方向-岗位技能","建筑工程",0]