[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277437":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1277437,867,3,"判断题","抹灰后要认真用托线板、靠尺对抹灰墙面尺寸预测摸底,统一阴阳角不同两个面的灰层厚度和方正,认真做好灰饼、冲筋;阴阳角处用方尺套方,做到墙面垂直、平顺、阴阳角方正。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"【知识点】 考察抹灰工程质量控制中墙面垂直度、平整度及阴阳角方正的处理方法。 【答案解析】 题干说法错误，因为抹灰前应进行基层处理并测量摸底，但“认真用托线板、靠尺对抹灰墙面尺寸预测摸底”应在抹灰前进行，而非抹灰后；且灰饼、冲筋用于控制抹灰层厚度和平整度，阴阳角方正需用方尺检查，但题干混淆了工序顺序。",{"id":6,"name":21,"category":22,"favorite":23},"装饰方向-岗位技能","建筑工程",0]