[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277376":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1277376,867,2,"多选题","建筑节能分部工程质量验收合格,应符合下列哪些规定( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","分项工程应全部合格",true,{"key":16,"text":17,"correct":14},"B","质量控制资料应完整",{"key":19,"text":20,"correct":14},"C","外墙节能构造现场实体检验结果应符合设计要求",{"key":22,"text":23,"correct":14},"D","严寒、寒冷和夏热冬冷地区的外窗气密性现场实体检验结果应合格",{"key":25,"text":26,"correct":14},"E","建筑设备工程系统节能性能检测结果应合格","ABCDE","【知识点】 建筑节能分部工程质量验收的合格条件 【答案解析】 正确答案为A、B、C、D、E。根据《建筑节能工程施工质量验收规范》，分部工程验收合格需满足分项工程全部合格、质量控制资料完整、外墙节能构造实体检验、外窗气密性现场实体检验及系统节能性能检测结果均符合要求，故五项均正确。",{"id":6,"name":30,"category":31,"favorite":32},"装饰方向-岗位技能","建筑工程",0]