[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277360":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1277360,867,2,"多选题","在正式施工前进行的事前主动质量控制,通过( ),分析可能导致质量目标偏离的各种影响因素,针对这些影响因素制订有效的预防措施,防患于未然。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","编制施工质量计划",true,{"key":16,"text":17,"correct":14},"B","明确质量目标",{"key":19,"text":20,"correct":14},"C","制订施工方案",{"key":22,"text":23,"correct":14},"D","设置质量管理点",{"key":25,"text":26,"correct":14},"E","落实质量责任","ABCDE","【知识点】 考察施工质量事前主动控制的具体措施。 【答案解析】 事前主动控制通过编制施工质量计划、明确质量目标、制订施工方案、设置质量管理点和落实质量责任，全面预防质量偏差，故A、B、C、D、E均正确。",{"id":6,"name":30,"category":31,"favorite":32},"装饰方向-岗位技能","建筑工程",0]