[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277357":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1277357,867,2,"多选题","施工技术准备包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","熟悉施工图",true,{"key":16,"text":17,"correct":14},"B","组织设计交底和图纸审查",{"key":19,"text":20,"correct":14},"C","进行工程项目检查验收的项目划分和编号",{"key":22,"text":23,"correct":14},"D","审核相关质量文件",{"key":25,"text":26,"correct":14},"E","细化施工技术方案和施工人员、机具的配置方案","ABCDE","【知识点】 考察施工技术准备的具体内容。 【答案解析】 施工技术准备包括熟悉施工图、组织设计交底和图纸审查、项目划分和编号、审核质量文件以及细化施工方案和资源配置，故A、B、C、D、E均正确。",{"id":6,"name":30,"category":31,"favorite":32},"装饰方向-岗位技能","建筑工程",0]