[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277355":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1277355,867,2,"多选题","计量控制开工前要( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","建立和完善施工现场计量管理的规章制度",true,{"key":16,"text":17,"correct":14},"B","明确计量控制责任者和配置必要的计量人员",{"key":19,"text":20,"correct":14},"C","严格按规定对计量器具进行维修和校验",{"key":22,"text":23,"correct":14},"D","统一计量单位,组织量值传递,保证量值统一,从而保证施工过程中计量的准确",{"key":25,"text":26,"correct":27},"E","进行工程项目检查验收的项目划分和编号",false,"ABCD","【知识点】 考察施工项目计量控制开工前的准备工作内容。 【答案解析】 正确答案为A、B、C、D，均属于计量控制开工前必须建立和完善的管理制度、人员配置、器具校验及量值统一等基础工作；E属于验收阶段的工作，与开工前计量控制无关。",{"id":6,"name":31,"category":32,"favorite":33},"装饰方向-岗位技能","建筑工程",0]