[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277354":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1277354,867,2,"多选题","根据《建筑工程施工质量验收统一标准》GB50300-2001的规定,建筑工程质量验收应逐级划分为( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","配置必要的计量人员",false,{"key":16,"text":17,"correct":18},"B","单位（子单位）工程",true,{"key":20,"text":21,"correct":18},"C","分部（子分部）工程",{"key":23,"text":24,"correct":18},"D","分项工程和检验批",{"key":26,"text":27,"correct":14},"E","审核相关质量文件","BCD","【知识点】 建筑工程施工质量验收的层次划分 【答案解析】 根据GB50300-2001，建筑工程质量验收应逐级划分为单位（子单位）工程、分部（子分部）工程、分项工程和检验批，因此正确答案为B、C、D。A和E属于质量控制措施，不属于验收划分层级。",{"id":6,"name":31,"category":32,"favorite":33},"装饰方向-岗位技能","建筑工程",0]