[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277353":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},1277353,867,2,"多选题","工序是( )对工程质量综合起作用的过程,所以对施工过程的质量控制,必须以工序作业质量控制为基础和核心。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","人、材料",true,{"key":16,"text":17,"correct":14},"B","机械设备、施工方法",{"key":19,"text":20,"correct":21},"C","施工工艺、人员调度、社会因素和环境因素",false,{"key":23,"text":24,"correct":21},"D","自然因素","AB","【知识点】 考察施工过程质量控制中工序质量的影响因素。 【答案解析】 正确答案为A、B，因为工序质量由人、材料、机械设备、施工方法等直接施工要素综合决定，而C中的社会因素和D中的自然因素非直接可控的工序质量影响因素。",{"id":6,"name":28,"category":29,"favorite":30},"装饰方向-岗位技能","建筑工程",0]