[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277348":3},{"question":4,"library":33},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":31,"analysis":32},1277348,867,2,"多选题","现场质量检查的内容包括( )。",[11,15,18,21,24,27],{"key":12,"text":13,"correct":14},"A","开工前的检查,主要检查是否具备开工条件,开工后是否能连续正常施工,能否保证工程质量",true,{"key":16,"text":17,"correct":14},"B","工序交接检查,对于重要的]二序或对工程质量有重大影响的工序,应严格执行",{"key":19,"text":20,"correct":14},"C","检”制度（即自检、互检、专检）,未经监理工程师（或建设单位项目技术负责人）检查认可,不得进行下道工序施工",{"key":22,"text":23,"correct":14},"D","隐蔽工程的检查,施工中凡是隐蔽工程必须检查认证后方可进行隐蔽掩盖",{"key":25,"text":26,"correct":14},"E","停工后复工的检查。因客观因素停丁或处理质量事故等停工复工时,经检查认可后方能复工",{"key":28,"text":29,"correct":30},"F","分项、分部丁程完工后的检查,应经检查认可,并签署验收记录后,才能进行下一工序的施工",false,"ABCDE","【知识点】 现场质量检查的内容分类。 【答案解析】 正确答案为A、B、C、D、E，均属于现场质量检查的典型内容，涵盖开工前、工序交接、三检制、隐蔽工程和复工检查；F选项虽合理，但属于分项分部验收，不属于现场质量检查的直接内容，故排除。",{"id":6,"name":34,"category":35,"favorite":36},"装饰方向-岗位技能","建筑工程",0]