[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277340":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1277340,867,2,"多选题","设定质量控制点,质量控制的目标及工作重点是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","要做好施工质量控制点的事前质量预控工作",true,{"key":16,"text":17,"correct":18},"B","产品质量不稳定和不合格率较高的工序应列为重点,认真分析,严格控制",false,{"key":20,"text":21,"correct":14},"C","要做好施工质量控制点的动态设置和动态跟踪管理",{"key":23,"text":24,"correct":18},"D","对施工现场存在的重大安全隐患未向建设主管部门报告",{"key":26,"text":27,"correct":14},"E","要向施工作业班组进行认真交底,使每一个控制点上的作业人员明白作业规程及质量检验评定标准,掌握施工操作要领","ACE","【知识点】 考察施工质量控制点的设置、管理及质量预控工作的要点。 【答案解析】 正确答案为A、C、E，它们分别体现了质量控制点的事前预控、动态管理和作业交底等核心工作；B项是控制点选取的原则而非工作重点，D项属于安全隐患报告问题，与质量控制点无关。",{"id":6,"name":31,"category":32,"favorite":33},"装饰方向-岗位技能","建筑工程",0]