[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277337":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1277337,867,2,"多选题","抹灰工程的施工质量控制点的预防措施有( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","基层应清理干净,抹灰前要浇水湿润,注意砂浆配合比,使底层砂浆与楼板粘结牢固;抹灰时应分层分遍压实,施工完后及时浇水养护",true,{"key":16,"text":17,"correct":14},"B","抹灰前要认真用托线板、靠尺对抹灰墙面尺寸预测摸底,安排好阴阳角不同两个面的灰层厚度和方正,认真做好灰饼、冲筋",{"key":19,"text":20,"correct":14},"C","踢脚板、墙裙施工操作要仔细,认真吊垂直、拉通线找直找方,抹完灰后用板尺将上口刮平、压实、赶光",{"key":22,"text":23,"correct":24},"D","在墙面和地面相交的阴角处,出地面管道根部和地漏周围,应先做防水附加层",false,{"key":26,"text":27,"correct":14},"E","要采用同品种、同强度等级的水泥,严禁混用,防止颜色不均;接槎应避免在块中,应甩在分格条外","ABCE","【知识点】 考察抹灰工程施工质量控制点的预防措施。 【答案解析】 正确答案为A、B、C、E，均属于抹灰工程中针对基层处理、平整度、细部收口及材料一致性等质量通病的预防措施；D项是防水工程措施，与抹灰无关，故排除。",{"id":6,"name":31,"category":32,"favorite":33},"装饰方向-岗位技能","建筑工程",0]