[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277272":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1277272,867,1,"单选题","隐蔽工程在隐蔽前应由( )通知有关单位进行验收,并应形成验收文件。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":21},"C","施工单位",true,{"key":23,"text":24,"correct":14},"D","设计单位","【知识点】 考察隐蔽工程验收的程序责任主体。 【答案解析】 正确答案是C（施工单位）。根据规范，隐蔽工程在隐蔽前应由施工单位通知有关单位验收，因为施工单位是施工活动的直接实施者，负有自检和报验的责任。",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]