[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277261":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1277261,867,1,"单选题","钢网架结构总拼完成后及屋面工程完成后应分别测量其( ),且所测( )不应超过相应设计值的( )倍。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","刚度值刚度值1.15",false,{"key":16,"text":17,"correct":18},"B","挠度值挠度值1.15",true,{"key":20,"text":21,"correct":14},"C","刚度值挠度值1.2",{"key":23,"text":24,"correct":14},"D","挠度值刚度值1.2","【知识点】 钢网架结构挠度测量及验收标准。 【答案解析】 正确答案为B。钢网架结构总拼及屋面完成后应测量挠度值，且实测挠度不应超过设计值的1.15倍，故选B。",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]