[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277254":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1277254,867,1,"单选题","建设工程项目质量控制体系,一般形成( )的结构形态,这是由其实施任务的委托方式和合同结构所决定的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","全方位、多单元",false,{"key":16,"text":17,"correct":14},"B","全方位、立体化",{"key":19,"text":20,"correct":21},"C","多层次、多单元",true,{"key":23,"text":24,"correct":14},"D","多层次、立体化","【知识点】 建设工程项目质量控制体系的结构形态及其决定因素。 【答案解析】 正确答案为C，因为质量控制体系由委托方式和合同结构决定，形成多层次（如总包、分包层级）和多单元（各子项目或合同段）的结构形态。",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]