[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277253":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1277253,867,1,"单选题","( )是项目质量目标、责任和措施分解的必然结果。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","多层次结构",false,{"key":16,"text":17,"correct":18},"B","多单元结构",true,{"key":20,"text":21,"correct":14},"C","整体性结构",{"key":23,"text":24,"correct":14},"D","立体化结构","【知识点】 考察项目质量计划编制中质量目标分解的结构形式。 【答案解析】 正确答案是B，项目质量目标、责任和措施需按项目结构分解为多单元，形成多单元结构，以实现逐层落实。",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]