[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277228":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1277228,867,1,"单选题","对建设工程项目而言,不属于直接影响建设工程项目质量的管理环境为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工现场的通风",true,{"key":16,"text":17,"correct":18},"B","多单位、多专业交叉协同施工的管理关系",false,{"key":20,"text":21,"correct":18},"C","组织协调方式",{"key":23,"text":24,"correct":18},"D","质量控制系统","【知识点】 考察建设工程项目质量管理中管理环境因素的识别。 【答案解析】 正确答案为A。施工现场的通风属于物理作业环境，而非管理环境；管理环境指多单位协同关系、组织协调及质量控制系统等，故A不属于直接影响的管理环境。",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]