[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277227":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1277227,867,1,"单选题","对于建设工程项目管理者而言,( )、管理和环境因素,是可控因素。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","机器",false,{"key":16,"text":17,"correct":18},"B","人、技术",true,{"key":20,"text":21,"correct":14},"C","资金",{"key":23,"text":24,"correct":14},"D","施工日期","【知识点】 考察建设工程项目管理的可控因素分类。 【答案解析】 正确答案是B，因为人、技术和管理是项目管理者可直接控制和调整的核心因素，而机器、资金、日期等受外部条件制约较多，可控性相对较低。",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]