[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277225":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1277225,867,1,"单选题","施工质量控制应贯彻全面、全过程质量管理的思想,运用( )原理,进行质量的事前控制、事中控制和事后控制。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","动态控制",true,{"key":16,"text":17,"correct":18},"B","静态控制",false,{"key":20,"text":21,"correct":18},"C","自动控制",{"key":23,"text":24,"correct":18},"D","科技控制","【知识点】 考察施工质量控制的基本原理，即动态控制原理。 【答案解析】 正确答案是A。施工质量控制强调全过程管理，需根据实际情况动态调整，事前、事中、事后控制均体现动态循环，而非静态或自动控制。",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]