[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277220":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1277220,867,1,"单选题","控制的重点是发现( ),并通过分析提出施工质量改进的措施,保持质量处于受控状态。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工质量方面的缺陷",true,{"key":16,"text":17,"correct":18},"B","管理方面的缺陷",false,{"key":20,"text":21,"correct":18},"C","施工技术的不足",{"key":23,"text":24,"correct":18},"D","存在的安全隐患","【知识点】 施工质量控制中“控制”的核心任务与重点。 【答案解析】 控制重点在于发现施工质量方面的缺陷（选项A），因为质量控制直接针对质量偏差，通过分析这些缺陷来改进措施，保持质量受控；管理、技术或安全隐患虽相关，但不是本题所指的直接控制重点。",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]