[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1277218":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1277218,867,1,"单选题","施工技术准备是指在正式开展( )前进行的技术准备工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量检测",false,{"key":16,"text":17,"correct":18},"B","施工作业活动",true,{"key":20,"text":21,"correct":14},"C","进度检查",{"key":23,"text":24,"correct":14},"D","安全检查","【知识点】 施工技术准备的定义与时机。 【答案解析】 正确答案是B。施工技术准备是在施工作业活动开始前进行的技术性准备工作，旨在确保施工条件具备，而非针对检测、检查等后续环节。",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]